Integration of solar PV plants into the distribution utility SCADA system: RTU installation, protection relay communication and energy monitoring.
- Solar PV plants integrated · KCETAŞ
- 2
Connecting a solar power plant to the grid does not end with installing the panels. The plant must appear in the distribution utility's SCADA system with the right signals and the right time stamps — only then can the operator detect a fault without sending a crew to site.
At two solar PV plants in the KCETAŞ distribution region we installed SCADA in the distribution substation buildings using Siemens SICAM A8000 CP-8031 RTUs, and established communication with the plants' Schneider Electric Easergy P3 protection relays through these RTUs. After checking every field signal and completing communication and functional tests, both plants were integrated into the KCETAŞ SCADA system.
Capabilities
- RTU installation in solar PV distribution substation buildings
- Protection relay communication integration
- Integration into the distribution utility SCADA system
- Signal, communication and functional testing
- Energy monitoring and power quality tracking
Reference projects
SEDAŞ SCADA Expansion Project
SEDAŞ distribution region, Türkiye
Under the SEDAŞ SCADA Expansion Project we designed and manufactured in-house the Hitachi Energy RTU530 based SCADA panels for 109 substatio...
Learn more
SEDAŞ Cyber Security Project
SEDAŞ distribution region, Türkiye
Under the Cyber Security Project delivered for SEDAŞ we renewed the protection, control and communication infrastructure of 152 substations....
Learn more
UEDAŞ 2026 SCADA Project
Bursa, Balıkesir, Çanakkale and Yalova, Türkiye
Under the UEDAŞ 2026 SCADA Project we carry out the engineering and field implementation work at 200 substations. The scope covers the insta...